Pointe West

Vero Beach, FL

www.PointeWestFlorida.com


Conception Date: Sept. 1997
Conceptual Approval: Mar. 1999

Golf Course

Construction Begin: Sept. 1999
Construction Completed: Oct. 2000

North Village

Platted: Feb. 2000
Infrastructure Completed: Nov. 2000
Residential Build Out: Aug. 2006

Central Village

Platted: May 2000
Infrastructure Completed: Oct. 2004
Residential Build Out: Fall 2006

South Village

Platted: Aug. 2004
Infrastructure Completed: Feb. 2005
Residential Build Out: Summer 2008

East Village (Pending)

Platted: Jul. 2006
Phase I Infrastructure
Completed:
Aug 2006
All Infrastructure
Completed:
Spring 2008
Residential Build Out: 2010

Commercial: Town Center (Pending)

Begin Construction: Fall 2006
Scheduled Completion: Fall 2008

Commercial: State Rd. 60 (Pending)

Begin Construction: Spring 2007
Scheduled Completion: Spring 2009
Aerial Taken: Feb. 2006